February 2018 – Work weekend

In the cold wind of February we started our work weekend. The plan was to replace 3 or 4 panels of the older track, starting from the new track on the front straight heading back towards the station.

Thanks to the “heavy gang” that work on Sundays for us, we managed to surpass the station and replace track all the way back past the level crossing to garden centre. It meant that we had to build a new level crossing, but we were happy to live with that minor inconvenience!

The plan now for the work weekend in October is to start at the other end of the front straight and work round Windmill Curve towards the diamond crossing.